Surrey County Council, Waverley Borough Council and Farnham Town Council are working together to tackle issues such as congestion and air quality in Farnham and its surrounding areas. This is called the Farnham Infrastructure Programme.
These councils meet on the Farnham Board to discuss the status of the programme and to agree the path forward
The Borough isn't finished but it is open.
Ringway ran out of paving slabs in February so the decision was made to get The Borough reopened ASAP with a temporary surface and return later to finish the works, all works are still due for completely by the end of November. At the time the decision was made there was no clarity on when the materials would be available, the work done on East Street by Crest Nicholson the delivery time quoted was 12 weeks and has been variable.
There are still snagging items on all of the sections that have been worked on so far, particularly associated with utility companies on Downing Street which are due to be addressed, these assets are owned by the utility companies and Surrey County Council cannot do the work for them as the Highway Authority.
The permanent lights at the Royal Deer junction are still being installed, this work will be complete by the end of April, which was the original schedule. Once all three sets of lights are working together (Longbridge, top of Downing Street and the Royal Deer), flows should improve, although whilst work is still on-going on Castle Street requiring temporary lights there will still be disruption.
Overnight resurfacing will begin in April, the roads to be resurfaced are South Street, Union Road, Victoria Road, West Street, The Borough and the Royal Deer Junction - when the dates are settled and the weather looks good there will be more detailed signage in town. I am sure many of us will be relieved to see that done, particularly South Street.
The two new two way sections take traffic out of the gyratory but allowing residents from the south to into the Waggon Yard car park and out again without going on along the narrow north / south section of Downing Street or the Narrow section of The Borough - both of which were pollution hot spots, because of the canyon effect between the buildings.
The loading bays that have been installed are for deliveries not for residents to park in.
The project team advised that work needed to start on Castle Street as Ringway had run out of paving and Castle Street is to be done in Yorkstone to reflect the conservation area and the view to Farnham Castle. The project team also advises that they are relooking at the planting areas and the underground services in those areas and that they will rework the design of the area outside the Tellers Arms (which was a bank when the design was "fixed").
The project team advised that Ringway had run out of paving slabs and therefore proposed to bring forward the work on Castle Street and open The Borough on schedule at the end of March with temporary tarmac on the pavements / loading bay to later be replaced by paving.
The Royal Deer Junction will reopen but with temporary lights, the permanent lights will be installed by the end of April
The project team advised that issues have been identified at the Royal Deer Junction where they are currently working.
These issues are serious and require two utility companies to undertake significant remedial works which mean that the resource that has been mobilised needs to be reallocated to continue to push to complete the works as quickly as possible.
A plan agreed between the Project Team and Ringway (the contractor) has been shared with Councillors – this is an operational decision and therefore determined by Officers not Councillors.
Councillors questioned why the team that were working on the Royal Deer Junction couldn't be moved on the closed section of The Borough to accelerate reopening. The Project Team has confirmed that this was reviewed but because of the limited space another work team could actually slow progress with people getting in each other’s way.
Local Councillors on the Farnham Board also raised concerns about the removal of the Island at the bottom of Castle Street that was reinstated because of safety concerns the last time it was removed. Officers advised that it needed to be removed to facilitate the work in this area and that the end state design will include a narrower crossing point with better landing points on both sides and greater pedestrian sight lights.
The most impactful phase of the works was always going to be the closure of The Borough. Local Councillors fought hard to ensure that both the new 2-way sections were implemented before The Borough was closed.
Downing Street Reopened on schedule for the start of the Christmas Shopping period to support town centre businesses
The initial phase of works focused on introducing the two new 2-way sections, so that they could be used when section of the gyratory needed to be closed to facilitiate the works.
In order to introduce the changes in traffic flow an Traffic Regulation Order consultation was added, this was completed in 2024 all parts of the proposed changes were approved apart from the closure of Park Row to traffic, this element of the design was therefore descoped.
During 2023 a Hybrid option of A and B was developed and consideration was given to making Woolmead two way and closing East Street to traffic, but the swept path analysis of the bend on the Woolmead identified that this option was only deliverable with land being taken from the Woolmead site. This option was therefore excluded from the Farnham Infrastructure Project for delivery with the Woolmead site.
The Consultation over the Summer of 2022 considered two options for the Town Centre - Option A and Option B (see images below). The support for both was broadly similar. Several techiques were employed during the consultation including an online consultation, social media consultation and the use of Virtual Reality so that residents could experience walking through the proposed design. The results of the consultation were summarised in this report - Item 4.1 Town Centre Consultation Report.pdf
https://www.surreysays.co.uk/.../farnham-town-centre.../
https://www.surreysays.co.uk/.../upper-hale-road-farnham.../
The Farnham Board and the Programme Team where provided the Final Draft of the Optimised infrastructure Plan for review on the 17th of September, 7 days before the Farnham Board meeting on the 24th of September.
During the Farnham Board Meeting on the 24th of September, it was agreed that the programme should proceed on the basis of the Final draft subject to comments form the board members (Farnham Infrastructure Board (Hybrid Meeting) 24th September 2021 - YouTube )
The final version was published in October 2021 and can be accessed via the link below
A31
The FIP Team advised that they are still working on options which will be shared and consulted with stakeholders, which will include Councillors across the 3 Councils and Officers as well as other stakeholders before submission of the Strategic Outline Business Case (SOBC) to the DfT in November 2021.
Completion by 2028
This project now also includes the Water Lane roundabout (verbally advised by Chris Greenwood during the 24th of September Farnham Board meeting).
Town Centre – this now incorporates the LCWIP work
Final Draft of the OIP includes a scheme that doesn't focus on full pedestrianisation. This was broadly welcomed by the Board. There are still some that are keen to see full pedestrianisation.
The programme team will consult on their detailed proposals in the coming months
Wrecclesham bypass and Western Link
Initial work has been completed by the Programme team but not yet shared.
The Public Consultation closed on the 14th of March
Consultation meetings on the draft OIP
10-Mar-21 Businesses in Farnham
Watch webinar, Presentation slides,Presentation notes
10-Mar-21 Facebook Live
Facebook Live recording, Presentation slides, Presentation notes
08-Mar-21 Farnham Infrastructure Programme Local Liaison Forum
Watch webinar, Presentation slides
04-Mar-21 Farnham Infrastructure Programme Local Liaison Forum
Watch webinar, Presentation slides
Local Liaison Forums
14-Jan-20 - 3:00pm - Young people and Youth organisations / Schools
Watch webinar, Presentation slides
07-Jan-21 - 6:30pm - Wrecclesham
Watch webinar, Presentation slides , Presentation notes
06-Jan-21 - 6:30pm - North Farnham
Presentation notes , Watch webinar
06-Jan-21 - 3pm - A31 Hickley's Corner
Presentation notes, Watch the webinar
09-Dec-20 - 6.30pm - Town Centre
25-Nov-20 - Community meeting
Watch the webinar, Presentation notes
02-Nov-20 - Businesses in Farnham
21-Oct-20 - Residents’ Associations and The Farnham Society
Launch of Farnham Infrastructure Programme
05-Aug-20 - Launch the Farnham Infrastructure Programme
Watch the webinar,Presentation notes,Questions and answers,Other questions submitted prior to meeting
Surrey wants to restrict onstreet parking – but do parked cars help keep pedestrians safe ?
The Farnham Herald, Thursday 3rd December 2020 - Vol.130 No.22
by Catherine Powell
Upper Hale resident, chartered engineer and founder of North Farnham Voice
THE VILLAGES of north Farnham have been there for hundreds of years – but are now blighted by poor road infrastructure, limited poorly maintained narrow pavements, minimal cycle paths and fast moving-traffic including heavy goods vehicles (HGVs).
One recent survey of local residents found the area “feels neglected and under-resourced compared with elsewhere in the town”.
The message is we need to get out of our cars and get around in other ways, use public transport, walk or cycle. But there are infrequent buses which are prohibitively expensive for some to use.
A return fare from Sandy Hill to the hospital for a parent and two kids under 15 is more than £10, and that is the nearest doctor’s surgery.
Safe walking routes between residential areas and local shops, schools and facilities are almost non-existent and there are limited crossings on the Upper Hale Road and Farnborough Road. The fast-moving traffic often means making a run for it and not everyone is up to that – nor is it safe.
Why don’t more kids cycle to school, they say! Where are the safe cycle route ?
North Farnham residents are, however, coming together to make their voices heard with the North Farnham Voice Group. There is already a Facebook page ( www.facebook.com/groups/northfarnhamvoice ) and plans are afoot for a website.
Residents support the proposal to ban HGVs greater than 7.5 tonnes as proposed under the Farnham Infrastructure Programme, and the need to refresh the speed signage with 20mph zones. However, there are lots of other issues that need to be discussed and addressed.
Proposals to reduce on-carriageway obstructions, including on-street parking, are not supported, as residents want less slower traffic and not faster traffic.
The on-street parking slows traffic down, in places shield pedestrians using the narrow pavements from traffic and helps with crossing the road.
Parking on the pavements is a problem as they are already too narrow in many areas for a pushchair or wheelchair.
The proposal to ban turning right from Upper Hale Road on to Alma Lane is not supported as it would again speed up traffic and just make other roads rat runs and many are very narrow although two way and have no pavements.
What is needed, in addition to banning HGVs, is more pedestrian crossings, traffic calming, reduced speed limits, cycle paths and more frequent and affordable public transport. There is also a real need for more community facilities for example a doctor’s surgery and more youth facilities.
■ Upper Hale residents are invited to have their say on proposed infrastructure changes at a Zoom meeting of the Local Liaison Forum on January 6. See www.farnham.gov.uk/towncouncil/llf for details.
The Farnham Herald, Thursday 26th November 2020 - Vol.130 No.21
23 November 2020: Proposed weight limit to restrict HGV journeys through Farnham
6 October 2020: Comment on plans to tackle transport and congestion in Farnham
11 August 2020: Forum gives people a voice (Farnham Town Council website)
Study recommendations presented to Farnham Board on 20th of November
What do you think?
Please do email (admin@northfarnhamvoice.uk) or post on our Facebook Page (https://www.facebook.com/groups/northfarnhamvoice)
Study recommendations presented to Farnham Board on 20th of November
In response to this analysis, our recommendations on the actions to follow are:
Short term / quick wins:
Provision of temporary loading bays (while Covid-19 restrictions are present)
Undertake speed survey of Upper Hale and Town Centre
Liaise with local business to understand willingness to consolidate deliveries in partnership with neighbours
Produce guide / protocol for loading and unloading in the town centre
Provide alternative mailboxes for local residents e.g. Amazon lockers
Implement VMS height warning at Wrecclesham Railway Bridge and
Restrict HGV through-trips via Castle Street / Folly Hill and Upper Hale via weight restriction on A287 (e.g. no vehicles over 7.5T)
To be considered as part of the OIP (longer term):
Introduction of micro-consolidation centres at local locations
Refresh speed signage in Upper Hale / School 20 mph zone (Upper Hale) / 20 mph zone subject to outcome of speed survey
Introduction of loading pads (with timed restrictions) on widened footways
Review of parking capacity variable message signing in town centre
Introduction of consolidation centre at strategic location
Upper Hale - introduction of scheme to reduce on-carriageway obstructions including on-street parking restrictions and / or one-way priority working sections and / or one way system and
Upper Hale - right turn ban (onto Alma Lane)